DOMINO CONSTRUCTION UPDATE: Weeks of January 7th and January 14th, 2018

At Site A the ground floor through 22th floor commercial and 28th floor Residential slabs are complete. Framing and rebar above the bridge has begun. This is a lengthy process and are expecting to pour the slabs at the end of the month. Utility work in the street on Kent avenue  is mostly complete with gas work wrapping up in the spring. MEP trades will continue their overhead and in deck work. Precast Facade erection has begun on a second shift and will end prior to 10pm every evening. The facade is wrapping the building from bottom up. Interior fitouts have begun on the 5th floor and will work their way up the building.

The Refinery shoring work has begun. This will consist of steel structures on the exterior to brace the existing brick façade during demolition.

Construction of the Domino Park is complete. The park has opened and has entrances on Grand Street, South 3rd Street and South 5th Street.

The public park located on Site C is open 6 days a week

This entry was posted in Construction Updates. Bookmark the permalink.