DOMINO CONSTRUCTION UPDATE: Weeks of March 18th and March 25th, 2019

At Site A the ground floor through 35rd floor slabs are complete. We will be pouring the 36th , 37th & 38th floor slab during these weeks. Topping out of the building is scheduled for the end of April. MEP trades will continue their overhead, riser and in deck work. Precast Facade erection has begun on a second shift and will end prior to 10pm every evening. The facade is wrapping the building from bottom up. Interior fitouts have begun on the 5th floor and will framing and sheet rocking on the 12th floor and working their way up the building.

The Refinery shoring work has begun. This will consist of steel structures on the exterior to brace the existing brick façade during demolition. The southern and northern towers are complete. Work is to begin on the west side of the structure shortly.

Construction of the Domino Park is complete. The park has opened and has entrances on Grand Street, South 3rd Street and South 5th Street.

The public park located on Site C is open 6 days a week

This entry was posted in Construction Updates. Bookmark the permalink.