DOMINO CONSTRUCTION UPDATE: Weeks of August 26th and September 2nd, 2019

At Site A the ground floor through 42nd floor slabs are complete. The bulkheads for the building are complete. MEP trades will continue their overhead, riser and fit out work. Precast Facade erection is complete except for the commercial hoist area. The remaining work will be completed in 2 shifts, one during daytime and a second from 3-10 pm. Interior fit outs have begun and framing and sheet rocking are working their way up the building. Kent Ave sidewalk is complete. South first street sidewalk will be poured mid September, with the road opening around the same time. Grand Street sidewalk will be poured mid to late September. Residential leasing office is now open, with a TUP and TPP in place. Residential lobby to be completed within the next 2 weeks. Inspections for future TCOs are being scheduled.

The Refinery shoring work is complete. This consists of steel structures on the exterior to brace the existing brick façade during demolition. Interior demolition has begun, and currently is on the 10th floor of the building, working their way down the building.

Construction of the Domino Park is complete. The park has opened and has entrances on Grand Street, South 3rd Street and South 5th Street.

The public park located on Site C is open 6 days a week

This entry was posted in Construction Updates. Bookmark the permalink.