DOMINO CONSTRUCTION UPDATE: Weeks of April 15th and April 22nd, 2019

At Site A the ground floor through 42nd floor slabs are complete. We will be pouring the bulkhead slabs during these weeks. Topping out of the building is scheduled for April 24th, this will conclude the concrete pouring operations. stripping, grinding and cleanup will continue for the next 2 weeks. MEP trades will continue their overhead, riser and firout work. Precast Facade erection will work 2 shifts, one during daytime and a second from 3-10 pm. The facade is wrapping the building from bottom up and is curently on the 28th floor. Interior fitouts have begun and framing and sheet rocking are on the 14th floor and working their way up the building. Sidewalk and ground floor facade work will begin in the next 2 weeks

The Refinery shoring work has begun. This will consist of steel structures on the exterior to brace the existing brick façade during demolition. The southern and northern towers are complete. Work on the west side of the structure is complete.

Construction of the Domino Park is complete. The park has opened and has entrances on Grand Street, South 3rd Street and South 5th Street.

The public park located on Site C is open 6 days a week

This entry was posted in Construction Updates. Bookmark the permalink.