DOMINO CONSTRUCTION UPDATE: Weeks of March 9th, 2020 and March 16th, 2020
At Site A the ground floor through 42nd floor slabs are complete. The bulkheads for the building are complete. MEP trades will continue fit out work in the commercial leg. Precast Facade erection is complete, except for the commercial hoist … Continue reading
Posted in Construction Updates
Comments Off on DOMINO CONSTRUCTION UPDATE: Weeks of March 9th, 2020 and March 16th, 2020