DOMINO CONSTRUCTION UPDATE: Weeks of April 6th, 2020 and April 13th, 2020
At Site A all major façade work is complete; work that remains is minor: caulking, finishing, and glass replacement as needed. MEP trades has halted their work on interior fit outs in the commercial leg of the tower in the … Continue reading