At Site A all major façade work is complete; work that remains is minor: caulking, finishing, and glass replacement as needed. MEP trades has halted their work on interior fit outs in the commercial leg of the tower in the face of Coronavirius. Lobbies on Grand St and South First St are both open. Sidewalks are installed on Kent Ave, South First St, and Grand St. River street sidewalk work has also stalled due to Coronavirius.
Refinery shoring work is complete; this consists of exterior steel structures to brace the existing façade during demo. Shoring to remain in place through demolition and through new construction. Demolition has reached the ground floor of the building and is ongoing, expected to be complete by summer 2020. Foundation permit has been pulled and work is starting.
The northwest portion of Site B is fenced off and open to the public for an exhibit with the Brooklyn Museum. The remaining, separate portion of the site is used for refinery construction staging.
Construction of Domino Park is complete. The entrances are on Grand St, South 5th St, and a new entrance on South 4th st. The South 3rd entrance has been closed for pedestrian safety during construction.
Site C is closed to the public.