DOMINO CONSTRUCTION UPDATE: Weeks of May 4th, 2020 and May 11th, 2020
At Site A all major façade work is complete. All remaining work, minor in its nature, has been halted due to Coronaviris. Lobbies on Grand St and South First St remain open. Sidewalks are installed on Kent Avenue, South First … Continue reading
Posted in Construction Updates
Comments Off on DOMINO CONSTRUCTION UPDATE: Weeks of May 4th, 2020 and May 11th, 2020