-
Recent Posts
- DOMINO CONSTRUCTION UPDATE- WEEKS OF NOVEMBER 9 AND NOVEMBER 16
- DOMINO CONSTRUCTION UPDATE- WEEKS OF OCTOBER 26 AND NOVEMBER 2
- DOMINO CONSTRUCTION UPDATE- WEEKS OF OCTOBER 12 AND OCTOBER 19
- DOMINO CONSTRUCTION UPDATE- WEEKS OF SEPTEMBER 28 AND OCTOBER 5
- DOMINO CONSTRUCTION UPDATE- WEEKS OF SEPTEMBER 14 AND SEPTEMBER 21
Daily Archives: July 28, 2020
DOMINO CONSTRUCTION UPDATE: Weeks of July 27th, 2020 and August 3rd, 2020
At Site A all major façade work is complete. All remaining work is minor in its nature. Lobbies on Grand St and South First St remain open. Sidewalks are installed on Kent Avenue, South First Street, River Street and Grand … Continue reading
Posted in Construction Updates
Comments Off on DOMINO CONSTRUCTION UPDATE: Weeks of July 27th, 2020 and August 3rd, 2020