DOMINO CONSTRUCTION UPDATE- WEEKS OF SEPTEMBER 19 AND SEPTEMBER 26
Tower Crane has been erected and is active on a daily basis. Concrete
superstructure and Steel Erection is ongoing. Exterior steel shoring towers
have begun removal now that new steel is in place. Exterior
masonry repairs are still in progress.
Site B is fenced off and is used for refinery construction staging. A
separate portion of site B is accessible off river street containing Domino
Park bathrooms and staffing/operations.
Construction of Domino Park is complete. The entrances are on Grand St,
South 1st St, and South 5th St.
Sites C and D excavation work is complete and foundation work is underway.