DOMINO CONSTRUCTION UPDATE- WEEKS OF SEPTEMBER 5 AND SEPTEMBER 12

Normal 0 false false false EN-US X-NONE X-NONE Tower Crane has been erected and is active on a daily basis. Concrete superstructure and Steel Erection is ongoing. Exterior steel shoring towers have begun removal now that new steel is in place.   Exterior masonry repairs are still in progress. Site B is fenced off and is used for refinery construction staging. A separate portion of site B is accessible off river street containing Domino Park bathrooms and staffing/operations. Construction of Domino Park is complete. The entrances are on Grand St, South 1st St, and South 5th St. Sites C and D excavation work is complete and foundation work is underway.