Monthly Archives: December 2022

DOMINO CONSTRUCTION UPDATE- WEEKS OF DECEMBER 12 AND DECEMBER 19

Tower Crane has been erected and is active on a daily basis. Concrete superstructure and Steel Erection is complete at the Refinery. Exterior steel shoring towers have begun removal now that new steel is in place.   Exterior masonry repairs are complete. Site … Continue reading

Posted in Construction Updates | Comments Off on DOMINO CONSTRUCTION UPDATE- WEEKS OF DECEMBER 12 AND DECEMBER 19