DOMINO CONSTRUCTION UPDATE- WEEKS OF NOVEMBER 28 AND DECEMBER 5

Tower Crane has been erected and is active on a daily basis. Concrete superstructure and Steel Erection is complete at the Refinery. Exterior steel shoring towers have begun removal now that new steel is in place.   Exterior masonry repairs are complete. Site … Continue reading