DOMINO CONSTRUCTION UPDATE:Week of August 11, 2014 and August 18, 2014

The Boiler House is undergoing Phase III mechanical demolition work. Excavators are staging construction debris along the north side of the building.On the west side of the Boiler House, workers aided by a man-lift are flame cutting steel from the exterior.

Building 16 is undergoing preparation for the removal of the Domino Sugar sign and demolition of the remaining portions of the building. Holes were cut into the north side of the structure to allow installation of a hoist. Scaffolding was erected on the west side of the structure.

The two underground storage tanks located in the vegetated field are undergoing excavation and removal. Excavators were moving soil and sorting metal debris.