DOMINO CONSTRUCTION UPDATE:Week of January 5th, 2015 and January 12th, 2015

Asbestos abatement is ongoing inside the Boiler House stacks. Mechanical demolition will resume once abatement is complete. Sorting and grading activities are ongoing throughout the Site.