DOMINO CONSTRUCTION UPDATE:Week of August 31st, 2015 and September 7th, 2015
The Refinery building continues to be hand demolished on the interior of the building. The removal of the bulkhead concrete decking along the river is pressing forward, work is progressing from the north end of the site to the south. … Continue reading