Hand demolition in The Refinery building is continuing. The removal of the bulkhead concrete decking on the river front is nearly complete. New piers are being installed in the east river to support the future bulkhead decking. Piers are being cut to final heights. The new sea wall is beginning installation. The public park located on Site C is open 6 days a week.
At Site E, superstructure concrete is underway and sections of the North and South tower deck and supporting columns are being poured daily. Concrete is on schedule to top out by the end of September All MEP trades are continuing deck work and coordination efforts. installation of CMU, exterior framing and MEP work is ongoing.