DOMINO CONSTRUCTION UPDATE:Week of July 25th, 2016 and August 1st, 2016

Hand demolition in The Refinery building is continuing. The removal of the bulkhead concrete decking on the river front is nearly complete. New piers are being installed in the east river to support the future bulkhead decking. Piers are being cut to final heights. The new sea wall is beginning installation. The public park located on Site C is open 6 days a week.

At Site E, superstructure concrete is underway and sections of the North and South tower deck and supporting columns are being poured daily. Concrete is on schedule to top out by the end of September All MEP trades are continuing deck work and coordination efforts. installation of CMU and horizontal MEP work is ongoing.