Hand demolition in The Refinery building is continuing. The removal of the bulkhead concrete decking on the river front is nearly complete. New piers are being installed in the east river to support the future bulkhead decking. Piers are being cut to final heights. The new sea wall is beginning installation. The public park located on Site C is open 6 days a week.
At Site E, superstructure concrete is underway and sections of the 11th floor slab on the south tower and supporting columns areĀ being poured daily. All MEP trades are continuing deck work and coordination efforts. installation of CMU and horizontal MEP work has begun.