DOMINO CONSTRUCTION UPDATE: Week of December 25th, 2017 and January 1st, 2018
At Site A Excavation and dewatering work is ongoing and SOE and pile driving is complete. Excavation and trucking of soil is continuing daily and production piles along with tie back installation has begun. Foundation footings have been poured and … Continue reading
Posted in Construction Updates
Comments Off on DOMINO CONSTRUCTION UPDATE: Week of December 25th, 2017 and January 1st, 2018