At Site A Excavation and dewatering work is ongoing and SOE and pile driving is complete. Excavation and trucking of soil is continuing daily and production piles along with tie back installation has begun. Foundation footings have been poured and are continuing to be installed. Underground plumbing work has begun.
Construction of the Domino Park is ongoing, including earthwork, utility work, and concrete. Electrical, Mechanical and plumbing work is ongoing. The elevated walk steel is complete and painting of the artifacts only needs touchup work. Pavers and precast planks have been delivered to site and are being installed. Finishes including light fixtures, handrails and millwork has begun. Paving of the new road had begun. Work is progressing from the north to the southern end of the site.
The public park located on Site C is open 6 days a week.
At Site E, All MEP trades are doing roughing and final installation. Installation of exterior cladding is nearly complete & interior framing and MEP work is ongoing. The northern hoist is being removed and cladding of the hoist run will begin immediately after. Mechanical rooms are completed and apartment fit out is ongoing. Final inspections throughout the building are completed for the South tower. Inspections for future TCOs are to be scheduled. The sidewalk on Kent Avenue is open to the public.