DOMINO CONSTRUCTION UPDATE: Week of April 16th, 2018 and April 23rd, 2018

At Site A Foundation work is complete and the foundation contractor has demobilized. Slab on grade and foundation walls for Site A are complete. Underground plumbing and electric work is complete. Superstructure Concrete has mobilized and pouring of the first section of ground floor slab has occurred and is continuing daily. The tower crane has been erected. The Con-Ed vaults will be installed on Kent Ave has begun this will reroute bike and pedestrian traffic for 3-4 weeks.

Construction of the Domino Park is ongoing, concrete sidewalk, pavers, railings and finish work. Electrical, Mechanical and plumbing work is ongoing and nearly complete. Pavers and precast planks have been delivered to site and are installed. Finishes including light fixtures, handrails and millwork is nearly complete. Paving of the new road had begun. The food kiosk construction is underway. Opening of the park is tentatively schedule for the beginning of June.

The public park located on Site C is open 6 days a week.

At Site E, the northern hoist has been removed and cladding of the hoist run is complete. Hoist run apartments are nearly complete.

This entry was posted in Construction Updates. Bookmark the permalink.