DOMINO CONSTRUCTION UPDATE: Weeks of November 12th and November 19th, 2018

At Site A the ground floor through 18th floor commercial and 23th floor Residential slabs are complete. There will be water, sewer and finalizing of Con-Ed work on Kent avenue during the coming few weeks. Sidewalk shed is erected. MEP trades will continue their overhead and in deck work. Precast Facade erection has begun on a second shift and will end prior to 10pm every evening. The facade is wrapping the building from bottom up.

Construction of the Domino Park is complete. The park has opened and has entrances on Grand Street, South 3rd Street and South 5th Street.

The public park located on Site C is open 6 days a week.

Site E construction is complete.