DOMINO CONSTRUCTION UPDATE: Weeks of March 4th and March 11th, 2019

At Site A the ground floor through 33rd floor slabs are complete. We will be pouring the 34th & 35th floor slab during these weeks. Topping out of the building is scheduled for the end of April. MEP trades will continue their overhead, riser and in deck work. Precast Facade erection has begun on a second shift and will end prior to 10pm every evening. The facade is wrapping the building from bottom up. Interior fitouts have begun on the 5th floor and will framing and sheet rocking on the 10th floor and working their way up the building.

The Refinery shoring work has begun. This will consist of steel structures on the exterior to brace the existing brick façade during demolition.

Construction of the Domino Park is complete. The park has opened and has entrances on Grand Street, South 3rd Street and South 5th Street.

The public park located on Site C is open 6 days a week.