DOMINO CONSTRUCTION UPDATE: Weeks of April 15th and April 22nd, 2019

At Site A the ground floor through 42nd floor slabs are complete. We will be pouring the bulkhead slabs during these weeks. Topping out of the building is scheduled for April 24th, this will conclude the concrete pouring operations. stripping, … Continue reading

Posted in Construction Updates

DOMINO CONSTRUCTION UPDATE: Weeks of April 1st and April 8th, 2019

At Site A the ground floor through 37th floor slabs are complete. We will be pouring the 38th, 39th floor slab during these weeks. Topping out of the building is scheduled for April 24th. MEP trades will continue their overhead, riser … Continue reading