DOMINO CONSTRUCTION UPDATE: Weeks of April 1st and April 8th, 2019

At Site A the ground floor through 37th floor slabs are complete. We will be pouring the 38th, 39th floor slab during these weeks. Topping out of the building is scheduled for April 24th. MEP trades will continue their overhead, riser … Continue reading