At Site A the ground floor through 42nd floor slabs are complete. The bulkheads for the building are complete. MEP trades will continue fit out work. Precast Facade erection is complete, except for the commercial hoist area of the commercial tower, which will remain open into the next calendar year. Interior fit outs continue in the commercial leg and the bridge. The Grand Street sidewalk has been poured but will remain behind a construction gate until the commercial lobby is opened within the month. The commercial lobby is expected to within the next couple of weeks. There are TCOs are in place and move in’s of the lower residential floors are occurring between 8 am and 5 pm. The commercial leasing team continues their leasing efforts.
The Refinery shoring work is complete. This consists of steel structures on the exterior to brace the existing brick façade during demolition. Interior demolition has begun and has reached the 4th floor of the building, working their way downward.
Construction of the Domino Park is complete. The park has opened and has entrances on Grand Street, South 3rd Street and South 5th Street.
The public park located on Site C is open 6 days a week