At Site A all major façade work is complete. All remaining work is minor in its nature. Lobbies on Grand St and South First St remain open. Sidewalks are installed on Kent Avenue, South First Street, River Street and Grand Street.
Refinery shoring work is complete; this consists of exterior steel structures to brace the existing façade during demo. Shoring to remain in place through demolition and through new construction. Demolition has reached the 2nd floor and is on-going.
The northwest portion of Site B is fenced off and open to the public for an exhibit with the Brooklyn Museum. The remaining, separate portion of the site is used for refinery construction staging.
Construction of Domino Park is complete. The entrances are on Grand St, South 5th St, and a new entrance on South 4th st. The South 3rd entrance has been closed for pedestrian safety during construction.
Site C is closed to the public.