DOMINO CONSTRUCTION UPDATE:Week of August 17th, 2015 and August 24th, 2015

Hand demolition in The Refinery building continues. The removal of the bulkhead concrete decking on the north end of the Site is pressing forward, work is progressing from the north end of the site to the south. They are also working on removing metal piers from the River.

The public park located on Site C is open 6 days a week.

At Site E excavation, load out, shoring and support of excavation work is occurring.

This entry was posted in Construction Updates. Bookmark the permalink.