DOMINO CONSTRUCTION UPDATE: Week of February 5th, 2018 and February 12th, 2018

At Site A Excavation and dewatering work is ongoing and SOE and pile driving is complete.Some foundation footings have been poured and are continuing to be installed. Slab on grade and foundation walls for Site A will be installed over the next month The underground garage foundation slab has been poured and walls are being formed and will be poured week of 12/12. Underground plumbing and electric work has begun. Superstructure Concrete is set to mobilize in March.

Construction of the Domino Park is ongoing, including earthwork, utility work, and concrete. Electrical, Mechanical and plumbing work is ongoing. The elevated walk steel is complete and painting of the artifacts only needs touchup work. Pavers and precast planks have been delivered to site and are being installed. Finishes including light fixtures, handrails and millwork has begun. Paving of the new road had begun. Work is progressing from the north to the southern end of the site.

The public park located on Site C is open 6 days a week.

At Site E, the northern hoist has been removed and cladding of the hoist run has begin immediately after. Hoist run apartments are finishing fitout. Mechanical rooms are completed and apartment fit out is ongoing. The sidewalk on Kent Avenue and south 4th street is open to the public.

This entry was posted in Construction Updates. Bookmark the permalink.