DOMINO CONSTRUCTION UPDATE: Week of March 5th, 2018 and March 12th, 2018

At Site A Excavation and dewatering work is Complete. Some foundation footings have been poured and are continuing to be installed. Slab on grade and foundation walls for Site A have begun and will be complete in the next 2 weeks. The underground garage structure has been completed. Underground plumbing and electric work has begun. Superstructure Concrete has mobilized. Tower crane will be erected on March23-25th. The Con-Ed vaults will be installed on Kent Ave at the end of March, this will potentially reroute bike and pedestrian traffic for 3-4 weeks.

Construction of the Domino Park is ongoing, concrete sidewalk, pavers, railings and finish work. Electrical, Mechanical and plumbing work is ongoing. Pavers and precast planks have been delivered to site and are installed. Finishes including light fixtures, handrails and millwork has begun. Paving of the new road had begun. The food kiosk construction is underway Work is progressing from the north to the southern end of the site.

The public park located on Site C is open 6 days a week.

At Site E, the northern hoist has been removed and cladding of the hoist run has begun immediately after. Hoist run apartments are finishing fitout. Mechanical rooms are completed and apartment fit out is complete.

This entry was posted in Construction Updates. Bookmark the permalink.